Wyman Park Building Renovation
Project Description
The Wyman Park Building renovation consists of constructing a new building core addition with new elevators and a multi-floor communicating stair. New rooftop mechanical equipment, interior and exterior renovations, including masonry cleaning and repointing, select window replacements, and a roof replacement, will also be included.
Project Schedule
Mobilization | Fall 2021 |
Core Addition Ground Work Begins | Fall 2021 |
Remove Roof AHUs | Summer 2022 |
Core Addition Topping Out | Fall 2022 |
Existing Loading Dock Repairs | Spring 2023 |
Project Completion | Winter 2023 |
Project Team
Chuck Hilseberg, senior project manager
Project Logistics
Traffic/Pedestrian Closures & Detours
- Construction traffic to enter/exit the site at 31st St.: right on Remington Ave., left on Wyman Park Dr. to Sisson St./29th St./I-83
- Construction workers will park at Johns Hopkins at Eastern on 33rd St. and will be shuttled to the job site daily
Project Updates
Construction Camera
Related Links/FAQs
- Site logistics plan
- Bathroom closures and temporary facilities key dates & plans
- Project schedule of key dates
- Main lobby renovation plans
- Town Hall Meeting recording: Oct. 19, 2021