Wyman 1 crane lift on Sat, Oct. 21 and Sun, Oct. 22

Due to rainy weather, the Wyman 1 crane lift originally scheduled for Saturday, October 14, has been rescheduled for Saturday, October 21. The demolition contractor reevaluated the amount of time required to complete the work and advised that the crane will be in operation for two consecutive days, Saturday, October 21, and Sunday, October 22. The estimated work hours are 7 a.m. and 5 p.m. on Saturday and 8 a.m. and 3 p.m. on Sunday.

The crane will be set up at the northwest corner of Wyman 1, the furthest point from W. 31st St.  Vehicular traffic will not be impeded. A temporary construction fence will surround the work area. A rain date has not been given. Please refer to the logistics plan below.

Chuck Hilseberg

Senior Project Manager
Contact
Email Address