Temporary Asphalt Path Installation on Sep 11
Please be advised that a temporary asphalt path will be installed between the E Gate Loop and the southeast stairs leading to the BLC Plaza on Thursday, September 11, 2025, from 7 a.m. to 7 p.m.
Scope of Work:
- Removal of existing woodchip surface along the current pedestrian path
- Installation of a new 6-foot-wide temporary asphalt path from the E Gate Loop to the southeast BLC stairs
Paths Impacted:
- The woodchip pathway will be closed to pedestrians during installation
- A detour route will be posted redirecting pedestrians to the BLC stairs
- ADA Pathway adjacent to the work area will remain open and unobstructed
Safety Measures:
- Detour signage will be installed at the Beach side of the pedestrian pathway
- Flaggers will be posted along the work zone to redirect pedestrian traffic
- Work zone will be clearly marked with appropriate barriers and fencing
Please refer to the logistics plan below: